Construction kicks off on BC’s North Coast Transmission Line, a major power project for the province’s northwest
Groundbreaking work has begun on a 330‑km transmission line that will double electricity supply in northern British Columbia, promising billions in economic gains and new jobs.
Early this week, massive excavators and crews of steel‑spine workers rolled onto the rugged terrain between Prince George and Terrace, officially breaking ground on what officials are calling the North Coast Transmission Line expansion. It’s not just another pole‑and‑wire project – it’s a promise of more than double the power that the remote north‑west of B.C. has been craving.
The line, now slated to stretch roughly 330 kilometres, will first tackle a 165‑kilometre stretch from Prince George out to near Fraser Lake, with a target finish date of 2030. A second phase will push the line the rest of the way to Terrace, aiming to be live by 2032. In plain terms, that means more reliable electricity for everything from looming LNG plants to the glittering mines of the Golden Triangle near the Alaskan border.
“This has gone from a concept to shovels in the ground in an incredibly short period of time,” said Tim Hodgson, Canada’s minister of Energy and Natural Resources, during a news conference in Prince George. He added that the project showcases what can happen when the federal, provincial and First Nations governments get together around a shared strategy.
British Columbia’s premier, David Eby, echoed that sentiment, warning that the United States has been hinting it wants to “break us economically so that they can take us over as the 51st state.” He said the new line is part of a broader effort to grow, diversify, and prove that Canada can meet the world’s clean‑energy needs without leaning on its southern neighbour.
Economically, the stakes are high. Provincial officials estimate the power boost could inject roughly $10 billion a year into B.C.’s economy, create about 9,700 jobs, and generate close to $950 million in municipal and provincial revenue. A loan of almost $140 million from the Canada Infrastructure Bank helped fast‑track pre‑construction work, while the federal and provincial governments together pledged $3.9 billion to see the project through.
There’s also a strong push for Canadian‑made material. Charlotte Mitha, chief executive of BC Hydro, said the utility is striving for “very, very high Canadian content” – even if it means re‑examining schedules to keep equipment sourced domestically wherever possible.
First Nations are set to play a key role, too. Co‑ownership agreements with the Lheidli T’enneh and other Nations are expected to be signed by the end of the year. “Today represents a new beginning for our region, our shared economy and our shared alignment of values,” said Chief Dolleen Logan of Lheidli T’enneh.
Beyond the numbers, the line could reshape how northern industries operate. With more power generated locally, mines and other heavy users will rely less on diesel, gaining cost certainty and a cleaner energy profile – a point Premier Eby highlighted as essential for long‑term competitiveness.
When asked about the ongoing trade tensions with the United States, Hodgson smiled and quoted an old adage: “Don’t get mad, get even.” He added, “Nothing would make me happier than the United States asking us for more electricity, while we proudly say, ‘We’ll keep it all right here.’”
All told, the North Coast Transmission Line is shaping up to be more than just a conduit for electrons. It’s a statement of intent – a tangible, humming line that says British Columbia is building its own future, one pole at a time.
Editorial note: Nishadil may use AI assistance for news drafting and formatting. Readers can report issues from this page, and material corrections are reviewed under our editorial standards.